The outside of the house hasn't really changed much apart from the front doors. One of the 'final' front doors has been installed, but I think he ran out of time before installing the second one.
On Friday morning I caught up with Steve and dropped off a Gainsborough 'Tri-lock' to replace the existing lock we had chosen for the front door. We were originally swaying to have a Tri-Lock as part of contract but the sales consultant at Hopetoun was not too savvy when it came to explaining the unit and we decided not to include it. Then later when we saw 'B&P's' comments we realised it would have the features we wanted so decided to ask 'F' if he could get it fitted for us which he kindly agreed to.
Shown below is one of the front doors fitted with the frosted glass to match the side lights.
The plasterers have finished the house and also included the Shower niches in both the Bathroom and ensuite.
The Plumber has also been back and rectified the issue with the washing machine taps. They have now been tucked inside the cabinet out of view. A bit of spak-filla over the hole and she'll be right mate! ;-)
Our stairs have now been installed and don't the kids love it! up and down, and up and down....
And here is a shot of the under-stairs storage area (AKA - the kids cubby)
Our balcony deck has been laid as well, and here we can see the cherubs conducting some stress testing. You'll also note how dusty they are? The place is a dust bowl - everything you touch has a layer of plaster dust on it.
As part of our variations we asked for the step height of the balcony deck to be raised up so that the cherubs wouldn't have to step off too deeply. You can see by the height in the picture below that the difference now is around 10mm or so - very happy with that.
All of the shelves have been added as well in all the cupboards, WIR and WIP as shown below.
And to our excitement so had our Quantum Quartz bench tops. The colour looks a little darker in this light but once all the paint is on and the place is cleaned up it should look beautiful. I have lifted off the protective chipboard for this shot.
Our kitchen sink has been dropped in place and the vanity units for the ensuite and B'room were both sitting in the family room waiting to be installed.
And finally here is the entrance to the rumpus room with the two doors added to minimise the sound. I may need to later update these to solid doors ;-)
6 comments:
Wow, all coming together nicely. Love the "kids cubby" :-)
Wow - sooo much progress in such a short time! It's all taking shape and looking great......:( so jealous...we don't even have a finished roof yet!!!!!!!!
What a week you've had !! Your girls are so cute !! I love how they're holding hands out there !
I like the little wall at the left side of the oven (sorry H2B!) - it closes off the kitchen nicely.
It all looks fantastic - you must be so pleased. CC
Thanks for all the pics, love looking at them. Love your front door ;-) Can't believe you have QQ already! Royal Base?
You must be pleased to see so much progress.
No worries CC ;-) I am so totally over my house I'm beyond caring. I love looking at everyone else's pics though.
I can't believe how quickly your place is happening. One thing about the Cremornes - they are all the same, but different! Yours is looking fantastic, and the kids look so happy! Thanks for all the photos.
Thanks Guys, yes we are pretty happy with the progress last week. And Yes HTB, the QQ is Royal Base. We can't wait for the paint to go on - it should really change the look of the place from the dull grey palster walls and to see the Tiles go on as well!