The 'bobcat man' has been out and tidied up the yard and removed all the plaster and other building materials, which has made a vast improvment across the site.
The moulding has been installed across the front facade...
...and the Render has also been applied to the balcony and looks Fantastic. We LOVE the colour. They have done a very neat job too.
Looking at the house from the outside now, it looks almost complete!
We have however run into a few more issues with the sparky. Things like the installation of downlights as mentioned last week and the one shown below. They seem to have made the hole too large and patched around it and the light fitting itself has sunk into the bog/ceiling. They have now fitted the downlights in the kitchen cabinets (previously in the ceiling) and also fitted the ranghood.
It appears they had some major problems with the wiring of the house too. Speaking with 'F', he said it would appear that someone has messed with the wiring and helped themsevles to some of it. As you'll see below, the Sparky has had to cut multiple sections out of the upstairs flooring to access the wiring to make repairs. Not happy Jan :-(
Here you can see that they have had to cut a hole in the plaster to access a junction box near the front door.
This is the section they had to remove in the Games room.
This is looking into the cut away section.
Here you can see the sections removed in the Master bedroom...
...and more in the same.
This is the area near the stairs.
And this is in one of the cherubs' bedrooms.
Yet again we have come across issues which exist beacuse of poor communications between the builder and the tradesmen. We spcified in the contract that we wanted 3 light fittings in the stairwell, each 300mm of the stair treads for us to install low voltage lights to illuminate the stairs at night. It seems that the tradesmen just get a plan diagram to work off and that's it. It merely shows a location from a plan view with no description of height and subsequently they mounted the light around 6 foot off the floor. After bringing this to 'Fs' attention, they have relocated the 3 fittings. I have indicated in the photo where the original holes were placed.
The rumpus room has finaly been finshed off, after they ripped down the wall and bulkhead, and the paint looks pretty good.
Our gas meter has also been installed and when we arrived today there were three blokes installing our ceiling insulation (2.5 batts). Chatting to one of them he was saying how tight it was in the ceiling due to all of the heating and cooling ducts. I don't think I'm gonna have much storage space up there. The tiling has not progressed at all this week but I assume they will be back next week to finish it off. I can't wait till the cleaner comes and gives the place a once over. As everything is covered an a layer of dust, nothing looks new.